Main Navigation Header Living Here - Fairfax County Homepage Doing Business in Fairfax County Visiting Fairfax County Fairfax County Government Using this Site Contact us

Lake Rehabilitations

Dam Safety Improvements
(Royal Lake, Woodglen Lake and Lake Barton)
Updated: March 2008

Royal Lake
Royal Lake Question and Answer
Royal Lake Presentation

Information Sheet #1
Information Sheet #2

Recently, Supervisor Bulova hosted a Pardon Our Dust meeting in anticipation of the construction set to begin at Royal Lake.
Here is some information that you might find helpful as construction begins!

Royal Lake Information

In addition to the plans for Royal Lake, there are also two other lakes being studied for future work: Woodglen Lake and Lake Barton.

The Woodglen Lake dam (constructed in 1981) and Lake Barton dam (constructed in 1978) are both located in the Braddock District. These dams were built to capture sediment and to prevent it from moving downstream. Today, neither lake meets today's design and safety criteria. While the chance for a structural failure is very remote, studies have shown that some residents and roadways would be at risk should there be a catastrophic failure of the dam. For this reason, the Virginia Department of Conservation and Recreation has issued a conditional operations certificate to the Fairfax County Board of Supervisors with the provision that the deficiencies must be addressed.

Woodglen Lake

The comment period for the watershed plan for the rehabilitation of Lake Barton has passed. Please watch this page for further updates re: the signing ceremony and construction information.


Lake Barton
The hydrologic and hydraulic (H&H) studies for Lake Barton have been completed and NRCS is in the process of developing draft planning documents using the results.

As part of the H&H study, a sediment survey was completed to estimate the sediment pool capacity. At the current time, the sediment pool has a projected life of 42 years. NRCS considered two alternatives for increasing sediment pool capacity to the minimum required 50 years: (i) raising the permanent pool elevation, and (ii) dredging. The preferred alternative is to raise the permanent pool 0.8 feet. This will have minimal impact on the recreational area around the lake and is considered to be the most cost-effective option. The H&H analysis showed that the permanent pool could be raised to this level without having to raise the auxiliary spillway crest which means that there would no impact on the existing floodplain. The preferred spillway rehabilitation option is to line the existing spillway with articulated concrete blocks and extend the spillway downstream. A conceptual layout was prepared as part of the H&H study, but the proposed alignment may be revised as the concept design is developed further. As part of the preliminary design, a number of options for construction access will be developed. It will be the County's preference to develop a permanent access road for future maintenance activities.


Keep watching this site for future updates!