  • International Drive & Greensboro Drive Pedestrian Access and Gosnell Road & Old Courthouse Road Pedestrian Access Improvements

    • Contract No. - CN15102007 & CN15102008
    • Project No. - 1400067-2012 & 1400071-2012
    • VDOT Project No. - UPC No. 103265 & 103282
    • Project Engineer - Lisa McCorkle
    • Contractor - Sagres Construction Corporation
    • Location - Providence & Hunter Mill
    • Scope - Construction of concrete sidewalk, median, curb, gutter, pedestrian curb ramps, pedestrian signal modifications, asphalt repair, pavement marking, restoration and other related items.
    • Completion - Jan. 2017
  • Wiehle Avenue/Dulles Toll Road WB Ramp Pedestrian Access Improvements

    • Contract No. - CN16102012
    • Project No. - AA1400097-2013, UPC No. 107436
    • Project Engineer - Juanpablo Quinteros
    • Contractor - Ardent Company, LLC
    • Location - Hunter Mill
    • Scope - Construction of a concrete sidewalk, combination curb & gutter CG-6, curb cut ramp standard CG-12A & 12B with detectable warning, PF-2 poles, mill and overlay, pavement marking and other related items
    • Completion - Late Fall 2016
  • Route 1 SB: Mount Eagle Drive Walkway
    Route 1 SB: Gregory Drive to Russell Road Walkway
    Route 1 NB: Frye Road to Radford Avenue Walkway
    Route 1 NB: Engleside Street to Forest Place Walkway

    • Contract No. - CN16102013, CN16102015, CN16102016, CN16102018
    • Project No. - AA1400081-2012, AA1400083-2012, AA1400084-2012, AA1400087-2012
    • Project Engineer - Demond Frazier
    • Contractor - Sagres Construction Corporation
    • Location - Mount Vernon
    • Scope - Construction of work including but not limited to: curb and gutter, sidewalks, retaining wall, storm drainage structure and pipe modifications, asphalt demolition and restoration, pavement markings, tree removal, water line modifications, and site restoration work. Scope of work also includes cleaning of storm structure and pipe flushing
    • Completion - March 2017
  • Annual Contract for Construction Services

    • Contract No. - CN16026001
    • Project Engineer - Wayne Kotter
    • Contractor - Ashburn Contracting Corporation
    • Location - Various
    • Scope - Construction of pedestrian and transportation projects including concrete curb and gutter, sidewalks, asphalt trails, storm and sanitary sewers, underdrains, pavement milling, asphalt pavement, concrete driveway aprons and driveways, pavement markings, signs, traffic signals, guardrail, fencing, retaining walls, excavation, grading, seeding, sodding, erosion and sediment controls and other related items
    • Completion - May 2017
  • Leesburg Pike/Colvin Run Road Pedestrian Access Improvement Project

    • Contract No. - CN15124015
    • Project No. - ST-000003-018
    • Project Engineer - Qais Bashir
    • Contractor - A&M Concrete Corporation
    • Location - Dranesville
    • Scope - Construction of intersection modification, lane widening, 203 linear feet of sidewalk, bus pads, and pedestrian accessibility improvements which involves significant site improvements including construction of soldier pile retaining walls, box culverts, storm drainage structures, fencing, and other related site improvements.  Signal modification improvements shall include new mast poles, pedestrian signals, electrical work, new signage, pavement markings, and other associated improvements
    • Completion - Dec. 2016
  • Mason Neck Trail - Segment 2B

    • Contract No. - CN14307297
    • Project No. - ST-000028-002
    • VDOT Project No. - EN98-029-145, PE101, PE102, RW-201 C503 Phase 2B
    • Project Engineer - Tommy Cutler & Andy Royse
    • Contractor - W.C. Spratt, Inc.
    • Location - Mason
    • Scope - Construction of approximately 9,900 linear feet of 8 foot wide asphalt trail along Gunston Road between Pohick Bay Drive and the entrance to Pohick Bay golf course.  Scope of work includes storm drainage structures, demolition and replacement of existing driveways, erosion and sediment control and restoration.
    • Completion - Aug. 2017
  • Route 1 Intersection Improvements

    Arlington Drive
    Lockheed Boulevard
    Sacramento Drive

    • Contract Nos. - CN14500026, CN14500027, CN14500028
    • Project Nos. - AA14-00016-06, AA14-00015-06, AA1400013-06
    • VDOT Project No. - 0001-029-930, P101 (UPC# 98753)
    • Project Engineer - Qais Bashir
    • Contractor - Arthur Construction Company
    • Location - Mount Vernon District
    • Scope - Construction of reinforced concrete foundation for future bus shelters, sidewalk and accessibility spot improvements associated with new stops, new crosswalks, multiple median cuts and curb ramps at existing crosswalks and sidewalk, and reconfiguration of lanes on Route 1, as needed, to provide median with accessible pedestrian refuge. Miscellaneous scope of work includes storm drainage structures, demolition and replacement of existing site improvements and erosion and sediment control measures.
    • Completion - Fall 2016
  • Cinder Bed Road Realignment

    • Contract No. CN15304081
    • Project No. 5G25-054-000
    • Project Engineer - Ben Samiyi
    • Contractor - Fort Myer Construction Corporation
    • Location - Lee District
    • Scope - Construction of a triple box culvert, concrete sidewalk, asphalt trail, curb and gutter, water line relocation, stream channel restoration and realign a portion of Cinder Bed Road and provide an access road into the Newington DVS maintenance facility.
    • Completion - Early Spring 2017
  • Soapstone Drive Walkway

    • Contract No. CN14124012
    • Project No. 1400019-2007
    • Project Engineer - Ben Samiyi
    • Contractor - Arthur Construction Co., Inc.
    • Location - Hunter Mill
    • Scope - Construction of approximately 3,000 linear feet of 5-foot wide concrete sidewalk. The project also includes related construction items such as asphalt pavement, drainage improvement, curb and gutter, excavation, and minor traffic signal work, handrail installation, pavement marking.
    • Completion - Aug. 2016
  • Route 123 & Braddock Road At-Grade Interim Improvements

    • Contract No. CN15124103
    • Project No. 2G40-015-000
    • Project Engineer - Michael Stevens
    • Contractor - Ardent Company, LLC
    • Location - Braddock & Springfield
    • Scope - Construction to include lane widening, mill and overlay, drainage improvements, traffic signal work, pedestrian access improvements, pavement markings, signagll 2016
  • Lee Highway - U.S. Route 29 - Phase III Widening

    • Contract No. CN15124101
    • Project No. 5G25-052-000 & 2G40-019-000
      VDOT PROJECT NO. 0029-029-R54
      UPC # 105397 (RS)
    • Project Engineer - Ben Samiyi
    • Contractor - Fort Myer Construction Corporation
    • Location - Braddock
    • Scope - This project will provide an additional travel lane north bound on Lee Highway, U.S. Route 29, between the intersection of Legato Road and Shirley Gate Road. Construction of this project will include approximately 8,650 feet of additional asphalt pavement, concrete sidewalk/asphalt trail, concrete curb and gutter, striping and signage, maintenance of traffic and associated utilities.
    • Completion - November 2017
  • Annual Contract for Transportation Construction Services

    • Contract No. CN14304064
    • Project No. N/A
    • Project Engineer - Wayne Kotter
    • Contractor - D&F Construction, Inc.
    • Location - Various
    • Scope - Construction of pedestrian and transportation projects including concrete curb and gutter, sidewalks, asphalt trails, storm and sanitary sewers, underdrains, pavement milling, asphalt pavement, concrete driveway aprons and driveways, pavement markings, signs, traffic signals, guardrail, fencing, retaining walls, excavation, grading, seeding, sodding, erosion and sediment controls and other related items.
    • Completion - June 2017
  • Annual Contract for Bus Shelters, Benches & Pads

    • Contract No. CN14124013
    • Project Engineer - Various
    • Contractor - Ashburn Contracting Corporation
    • Location - Countywide
    • Scope - Construction and installation of bus pads, bus shelters, trash cans, handrail, curb ramps, paving, seeding & mulching, pavement stripping and other related items.
    • Completion - April 2017

Contact Fairfax County: Phone, Email or Twitter | Main Address: 12000 Government Center Parkway, Fairfax, VA 22035
Technical Questions: Web Administrator

ADA Accessibility | Website Accessibility
Awards | FOIA | Mobile | Using this Site | Web Disclaimer & Privacy Policy | Get Adobe Reader
Official site of the County of Fairfax, Virginia, © Copyright 2016

Website Feedback Website Feedback    Globe with various flags representing Web site language translations   Language Translations

Return to Graphic Version