Transportation and Stormwater Projects Under Construction
-
Annual Contract for Construction Services
-
Contract No. CN09026001
-
Project Engineer - Various
-
Contractor - Ashburn Contracting Corp.
-
Location - Countywide
-
Scope - Construction of curb and gutter, sidewalk and trails, storm
and sanitary sewers, asphalt paving, asphalt milling, and other
miscellaneous items.
-
Completion - December 2011
-
Annual Contract for Stormwater Ponds and Flood Proofing
Improvements
-
Contract No. CN09318001
-
Project Engineer - Various
-
Contractor - Environmental Quality Resources, LLC
-
Location - Countywide
-
Scope - Construction consists of the replacement of RCP in dams,
rip rap, concrete structures, and the creation of wetland
environments in SWM facilities.
-
Completion - December 2011
-
Annual Contract for Stormwater Ponds and Flood Proofing
Improvements
-
Contract No. CN29318001
-
Project Engineer - Various
-
Contractor – Ashburn Contracting Corp.
-
Location - Countywide
-
Scope - Construction repair, and enhancement of multiple stormwater
ponds, storm drainage, stream restoration, and flood proofing
projects, including residential properties. Work includes
installing and replacing drainage pipes, dam repairs, and/or
construction, BMP retrofits, rip rap, concrete structures,
areaways, flood proofing walls, and the creation of wetland
environments in SWM facilities.
-
Completion – January 2012
-
Fairfax County Parkway/Sunrise Valley Drive
-
Contract No. CN08304368, Project No. 064288
-
Project Engineer - Todd Minnix
-
Contractor - Tavares Concrete Co., Inc.
-
Scope - This project provides for construction of a new dual left
turn lane on northbound Fairfax County Parkway at Sunrise Valley
Drive. Construction includes grading, paving, storm drainage,
traffic signals, overhead signal support structure, asphalt and
concrete sidewalks/trails, concrete curb and gutter, pavement
markings, signs and related items.
-
Completion - Spring 2011
-
Fairfax County Parkway/West Ox Road Intersection Improvement
-
Contract No. CN09304377, Project No. 064276
-
Project Engineer – Lisa McCorkle
-
Contractor – Arthur Construction Co., Inc.
-
Scope - This project provides for construction of a dual left turn
lane northbound and extension of the existing southbound right turn
lane at the intersection of Fairfax County Parkway and West Ox
Road. Construction includes grading, paving, storm drainage,
traffic signal, asphalt and concrete sidewalks/trails, concrete
curb and gutter, pavement markings, signs and related items.
-
Completion – Spring 2011
-
Mason Neck Trail, Segment 2A
-
Contract No. CN04307219, Project No. W00600 (W613)
-
Project Engineer – Mohammad Gharavi
-
Contractor - – E. E. Lyons Construction Co., Inc
-
Scope - The work includes installation of approximately 1,500 LF of
asphalt trail, storm drainage, handicap ramps, handrail, seed &
mulch and related items.
-
Completion – Spring 2011
-
Lake Barton Dam-Pohick Creek Dam No. 2 Spillway Improvement
Project
-
Contract No. CN10318209, Project No. FX4000 – PC013
-
Project Engineer – Mike Knizner
-
Contractor - Shirley Contracting Company, LLC
-
Scope - The major items of work consist of: (1) construct a secant
pile wall at the downstream end of the auxiliary spillway chute (2)
increase the length of the downstream training dike between the dam
and the auxiliary spillway; and (3) construct a cast-in-place
concrete wall at the downstream end of the control section which
will also raise the control height of the auxiliary spillway.
-
Completion – Summer 2011
-
Sequoia Section 2, Pond 1
-
Contract No. CN10316078, Project No. CU8001-CU012
-
Project Engineer – Qais Bashir
-
Contractor – Avon Corporation
-
Scope – This project involves the retrofit of an existing 1.8 acre
stormwater management facility. The overall project consists
of excavation of the existing dam embankment, sediment
forebay/micro-pool installation, storm drain outfall stabilization,
outlet structure retrofit, and selective upland and wetland
planting.
-
Completion – Summer 2011
-
Flatlick Confluence Stream Restoration
-
Contract No. CN10316076, Project No. CU8001 – CU016
-
Project Engineer – Qais Bashir
-
Contractor – Meadville Land Service, Inc.
-
Scope – Restore approximately 1,700 L.F of Flatlick Branch stream
through series of a rock structures, such as rock vanes, j-vanes,
and riffle structures. Works also includes re-grading stream
banks, re-vegetation and other related items.
-
Completion – Summer 2011
-
Schneider Branch Stream Restoration
-
Contract No. CN10316075, Project No. CU8001 – CU014
-
Project Engineer – Qais Bashir
-
Contractor – Avon Corporation
-
Scope – Restore approximately 887 L.F of Schneider Branch stream
through series of a rock structures, such as rock toes, j-hooks,
and riffle structures. Works also includes re-grading stream
banks, re-vegetation and other related items.
-
Completion – Summer 2011
-
Lake Barton Dredging Project
-
Contract No. CN10318204, Project No. FX4000 – PC019
-
Project Engineer – Mannan Quershi
-
Contractor – Lake Services of Virginia, Inc.
-
Scope – Mechanical dredging of 20,000 CY of sediment and an
additional 15,000 CY of sediment from Lake Barton with site
restoration after the dredging is completed.
-
Completion – Summer 2011