Upcoming Transportation and Stormwater Projects
Contact our branch at 703-324-5111, TTY 711.
Estimated Bid Date - Spring/Summer 2011
-
Seven Corners Transit Center
- Project No. 26007G
- Scope - Construct new bus transit transfer center at Seven Corners. Project includes federal funding.
-
Projected ad date is June 2010.
-
Columbia Pike Walkway - Phase II
- Project No. 26008G
- Scope - Construct new asphalt sidewalk, retaining wall, bus pad, and curb cut ramps on eastbound Columbia Pike from Holmes Run to Powell Lane. Project includes federal funding.
-
Projected ad date is June 2010.
-
Silverbrook Road Walkway
- Project No. 064273
-
Scope - Intersection improvement to configure turn lanes at
Silverbrook Road and Hooes Road intersection.
-
Annandale Acres Storm Drainage Project
- Project No. FX1000-CA003
-
Scope - 1100 linear feet storm sewer, ditch, and berm improvements
to alleviate house flooding.
-
Regional Pond S-05
- Project No. SU0005
-
Scope - Regional detention facility to provide improved water
quality and quantity.
-
Reston, Section 24
- Project NO. FX4000 - DF006
-
Scope - Dam Safety Projects, dam repair/retrofit.
-
Loftridge
- Project No. CA8000 - CA017
-
Scope - Retrofit with bio-retention facility and rehabilitate
eroded stream.
-
Big Rocky Run Phase II (CU920)
- Project No. CU8001 - CU003
-
Scope - Provide stream bank stabilization and restoration of 2500
linear feet of Big Rocky Run for improved water quality.
-
Tripps Run, Phase I
- Project No. CA8000 - CA016
-
Scope - Provide stream assessment of ~2500 linear feet of Tripps
Run. Provide stream stabilization and restoration of 1250 linear
feet for improved water quality.
-
Indian Run Stream Restoration
- Project No. CA8000 - CA031
-
Scope - Stream assessment, stakeholder involvement, and stormwater
outfall stabilization along 3000 linear feet of Indian Run to
improve water quality.
-
Flatlick Branch Stream Restoration
- Project No. CU8001 - CU001
-
Scope - 730 linear feet stream stabilization using bioengineering
techniques to alleviate severe erosion [308/Z00018- Z1320].
-
Sheffield-Hunt Outfall Basin
- Project No. PC8000 – PC006
-
Scope – Provide 800 LF of stream restoration using natural channel
design techniques and detention basin retrofit to improve water
quality.
-
Big Rocky Run II
- Project No. CU8000 – CU0009
- Scope – Provide 2,000 LF of stream restoration using natural channel design techniques to improve water quality


Website Survey