Building Plan Review Times

Listed below are the current review times and backlog for normally submitted plans to the Building Plan Review Division. Please note, times listed below are averages based on recent reviews and may not reflect your actual review time. The status of your plan may be found online, via e-mail or by contacting Building Plan Review at 703-222-0114, TTY 711.

Building Plan Review times for residential and commerical plans submitted under the Expedited Building Plan Review Program are guaranteed to be half of the total times noted below.

Plan Type Backlog (time from submission to assignment to a reviewer) Review Time (time from assignment to completion of full review) Total estimated time for first set of reviews
New single family dwellings (R# plans) 2 - 3 weeks 5 - 7 working days 4 - 5 weeks
Additions to single family dwellings (R# plans) 2 weeks 5 - 7 working days 3+ weeks

Tenant Layouts (Q# plans - non walk-thru)

3 - 4 weeks 3 - 4 weeks 6 - 8 weeks
New commercial buildings and additions (Q# plans) 3 - 4 weeks 4 - 6 weeks 7 - 10 weeks
Retaining walls and similar structures 2 weeks 1 week 3 weeks