Progress Photos - August 2005
Important News and Information
|
|
|
-
Overall project is 27 percent complete.
-
Painting of the trellis structure on top of the Judge's Parking
Lot wall continues.
-
Precast stone caps are 95 percent on the Judges' Parking Lot
wall.
-
All six concrete placements for Level 2 are complete.
-
One of the six concrete placements for Level 3 is complete.
-
Hydraulic bollards at the new Post 99 location are expected to be
operational by mid-September.
|
-
Alternate access/egress through the cafeteria is in place and
operational.
-
Storm and sanitary sewer work is in progress.
-
Perimeter wall backfill is 80 percent complete.
-
The fifth quarterly partnering session is scheduled for Sept. 21,
2005.
-
Work on the Handicap Parking Lot has begun.
|