Progress Photos - November 2005

Important News and Information

 
  • Overall Project is 34 percent complete.
  • Four of the six concrete placements for Level 4 are complete.
  • Perimeter wall backfill is 95 percent complete.
  • Handicap Parking Lot is complete.
  • Masonry block work has begun on the Lower Level.
  • Reshores have been removed on the Lower Level and approximately 30 percent have been removed on the first floor.
  • Mechanical ductwork, electrical cabinets, installation of conduit are in progress on the Lower Level.
  • Project is on schedule and on budget.