Progress Photos - January 2006
Important News and Information
|
|
|
-
Overall Project is 37 percent complete.
-
The overall structure is “Topped Out” – the last major structural
concrete placement was Jan. 27, 2006.
-
Perimeter wall backfill is 95 percent complete.
-
Reshores have been removed on the Lower Level, First Floor,
Second Floor and approximately 60 percent have been removed on
the Third Floor.
|
-
Mechanical ductwork, electrical cabinets, installation of conduit
are in progress on the Lower Level.
-
Masonry block work is 90 percent complete on the Lower Level.
-
Masonry block work has begun on the First Floor.
-
The expansion portion of the project is on schedule and on
budget.
|