Progress Photos - February 2006
Important News and Information
|
|
|
-
Overall Project is 40 percent complete.
-
The overall structure is “Topped Out” – the last major structural
concrete placement was Jan. 27, 2006.
-
A “Topping Out” ceremony was held Feb. 10, 2006.
-
Perimeter wall backfill is 95 percent complete.
-
All reshores have been removed.
-
Mechanical ductwork, electrical cabinets, installation of conduit
are in progress on the Lower Level and First Floor.
|
-
Masonry block work is 90 percent complete on the Lower Level.
-
Masonry block work has begun on the First Floor and at roof
parapets.
-
Metal stud framing has started throughout the building.
-
The expansion portion of the project is on budget but the latest
contractor schedule update indicates a 1.5 month delay. The
general contractor is working on a recovery schedule.
|