Progress Photos - February 2006


Important News and Information

 
  • Overall Project is 40 percent complete.
  • The overall structure is “Topped Out” – the last major structural concrete placement was Jan. 27, 2006.
  • A “Topping Out” ceremony was held Feb. 10, 2006.
  • Perimeter wall backfill is 95 percent complete.
  • All reshores have been removed.
  • Mechanical ductwork, electrical cabinets, installation of conduit are in progress on the Lower Level and First Floor.
  • Masonry block work is 90 percent complete on the Lower Level.
  • Masonry block work has begun on the First Floor and at roof parapets.
  • Metal stud framing has started throughout the building.
  • The expansion portion of the project is on budget but the latest contractor schedule update indicates a 1.5 month delay. The general contractor is working on a recovery schedule.

Progress Photos

pic1pic2pic3
pic4pic5pic6
pic7pic8pic9
pic10pic11pic12


Previous Month | Next Month
Courthouse Expansion Home




Contact Us: General (Office of Public Affairs) | Technical (Web Administrator) | Directed Inquiries (County Agencies)
Phone: County Main Number - 703-FAIRFAX (703-324-7329), TTY 711 | County Phone Listing

ADA Accessibility | Website Accessibility
Awards | FOIA | Mobile | Using this Site | Web Disclaimer & Privacy Policy | Get Adobe Reader
Official site of the County of Fairfax, Virginia, © Copyright 2011
Verizon Cybertrust Security Certified Logo;

Website Survey Website Survey    Globe with various flags representing Web site language translations   Language Translations

Return to Graphic Version