Progress Photos - March 2006
Important News and Information
|
|
|
-
Overall project is 45 percent complete.
-
Perimeter wall backfill is 95 percent complete.
-
All reshores have been removed.
-
Mechanical ductwork, electrical cabinets, installation of conduit
and cable trays are in progress on the Lower Level, Level 1,
Level 2 and Level 3.
-
Masonry block work is 90 percent complete on the Lower Level.
|
-
Masonry block work at the roof parapets is complete.
-
Miscellaneous masonry block work is ongoing throughout the
building.
-
Metal stud framing has started throughout the building.
-
The expansion portion of the project is on budget but the latest
contractor schedule update indicates a 45 to 50 day delay. The
general contractor is working on a recovery schedule.
|