Progress Photos - April 2006


Important News and Information

 
  • Overall Project is 48 percent complete.
  • Perimeter wall backfill is 95 percent complete.
  • Mechanical ductwork, electrical cabinets, installation of conduit and cable trays are in progress on all levels of the building.
  • Masonry block work is complete on the Lower Level.
  • Masonry block work at the roof parapets is complete.
  • Miscellaneous masonry block work is ongoing throughout the building.
  • Metal stud framing has started throughout the building.
  • Installation of the rails for the elevators are in progress.
  • Installation of gypsum wallboard has started on interior walls.
  • The expansion portion of the project is on budget but the latest contractor schedule update indicates a 50 day delay. The general contractor is working on a recovery schedule.

Progress Photos

pic1pic2pic3
pic4pic5pic6
pic7pic8pic9
pic10pic11pic12


Previous Month | Next Month
Courthouse Expansion Home




Contact Us: General (Office of Public Affairs) | Technical (Web Administrator) | Directed Inquiries (County Agencies)
Phone: County Main Number - 703-FAIRFAX (703-324-7329), TTY 711 | County Phone Listing

ADA Accessibility | Website Accessibility
Awards | FOIA | Mobile | Using this Site | Web Disclaimer & Privacy Policy | Get Adobe Reader
Official site of the County of Fairfax, Virginia, © Copyright 2011
Verizon Cybertrust Security Certified Logo;

Website Survey Website Survey    Globe with various flags representing Web site language translations   Language Translations

Return to Graphic Version