Overall Project is 48 percent complete.
-
Perimeter wall backfill is 95 percent complete.
-
Mechanical ductwork, electrical cabinets, installation of conduit
and cable trays are in progress on all levels of the building.
-
Masonry block work is complete on the Lower Level.
-
Masonry block work at the roof parapets is complete.
-
Miscellaneous masonry block work is ongoing throughout the
building.
|
-
Metal stud framing has started throughout the building.
-
Installation of the rails for the elevators are in progress.
-
Installation of gypsum wallboard has started on interior walls.
-
The expansion portion of the project is on budget but the latest
contractor schedule update indicates a 50 day delay. The general
contractor is working on a recovery schedule.
|