Progress Photos - May 2006
Important News and Information
|
|
|
-
Overall project is 51 percent complete.
-
Perimeter wall backfill is 95 percent complete.
-
Mechanical ductwork, electrical cabinets, installation of conduit
and cable trays are in progress on all levels of the building.
-
Chillers were moved into place on the Lower Level.
-
Cooling tower installation is ongoing.
-
Miscellaneous masonry block work is ongoing throughout the
building.
-
Face brick has started on the Chain Bridge Road elevation.
|
-
Metal stud framing has started throughout the building.
-
Installation of the rails for the elevators is in progress.
-
Escalator installation between the First and Second Floors is
ongoing.
-
Installation of gypsum wallboard has started on interior walls.
-
The expansion portion of the project is on budget but the latest
contractor schedule update indicates a 60 day delay. The general
contractor is working on a recovery schedule.
|