Progress Photos - June 2006
Important News and Information
|
|
| General:
-
Overall Project is 55 percent complete.
-
The expansion portion of the project is on budget but the latest
contractor schedule update indicates an 87 day delay.
|
|
| Lower Level:
-
Mechanical, electrical and plumbing rough-ins continue.
-
Detention hollow metal frames are in place and welding is in
process.
-
Hydraulic elevator work is in process.
First, Second and Third Floors:
-
Stair installation is in process with two of the six stairs
complete.
-
Mechanical, electrical and plumbing work is in process.
-
Traction elevators are complete.
-
Exterior brick veneer is in process on the First Level.
-
Stud walls and drywall are in process.
-
Door frames are being installed on all levels.
| Fourth and Fifth Floors:
-
Mechanical, electrical and plumbing rough-in continue.
-
Curbs, air handling unit pads and screen wall structures are in
place.
-
Exterior masonry is 60 percent complete.
Roof Level:
-
Base roofing is in place.
-
Finish roofing will resume after masonry is complete.
-
Cooling tower and chiller are in place.
|