Progress Photos - July 2006
Important News and Information
|
|
| General:
-
Overall Project is 56 percent complete.
-
The expansion portion of the project is on budget but the latest
contractor schedule update indicates a greater than 90 day delay.
|
|
| Lower Level:
-
Mechanical, electrical, plumbing rough-in work continue.
-
Detention hollow metal frames are in place and welding is in
process.
-
Hydraulic elevator work is in process.
-
Ceiling framing, paint and blockfill have started.
-
The fire pump and controller are on site.
First, Second and Third Floors:
-
Stair installation is in process with three of the six stairs
complete.
-
Mechanical, electrical, plumbing work is in process.
-
Traction elevators are complete.
-
Exterior brick veneer and precast is in process on all three
levels.
-
Stud walls and drywall are in process.
-
Door frames are being installed on all levels.
| Fourth Floor:
-
Mechanical, electrical, plumbing rough-in work continue.
-
Curbs, air handling unit pads and screen wall structure are in
place.
-
Framing at the courtroom pop-ups is underway.
-
Exterior masonry is 80 percent complete.
Fifth Floor:
-
Mechanical, electrical, plumbing rough-in work continue.
-
White brick at the 5th floor is near completion.
-
Stud walls have started.
Roof Level:
-
Tapered roofing is in place.
-
Work is ongoing in the elevator machine rooms.
-
Cooling tower and chiller are in place.
|