Progress Photos - September 2006
Important News and Information
|
|
| General:
-
Overall Project is 58 percent complete.
-
The expansion is expected to receive substantial completion in
April 2007 and overall project completion is now set for April
2008.
|
|
| Lower Level:
-
Mechanical, electrical, plumbing rough-ins continue.
-
Duct testing continues.
-
Insulation is starting.
First Floor:
-
Stair installation is in process with three of the six stairs
complete.
-
Mechanical, electrical, plumbing work is in process.
-
Exterior brick veneer and precast is in process.
-
Perimeter framing has started.
-
Window installation has begun.
-
Stucco mock-up in the courtyard has started.
-
Front entrance tube steel and canopy have been installed.
Second Floor:
-
Door frames, metal stud walls and bulkheads are continuing.
-
Overhead mechanical, electrical, plumbing rough-ins work
continue.
-
Brick veneer and precast installation is ongoing.
| Third Floor:
-
Door frames, metal stud walls and bulkheads are continuing.
-
Overhead mechanical, electrical, plumbing rough-ins continue.
-
Brick veneer and precast installation is ongoing.
Fourth Floor:
-
Mechanical, electrical, plumbing rough-in work continue.
-
Curbs, air handling unit pads and screen wall structure are in
place.
-
Air handling units three and 11 have been set.
-
Framing at the courtroom pop-ups is nearing completion.
-
Exterior masonry is complete.
-
Roofing work has resumed.
Fifth Floor:
-
Mechanical, electrical, plumbing rough-in work continue.
-
White brick installation is complete.
-
Stud walls have started.
Roof Level:
-
Work is ongoing in the elevator machine rooms.
|