Progress Photos - October 2006
Important News and Information
|
|
| General:
-
Overall Project is 60 percent complete.
-
The expansion is expected to receive substantial completion in
April 2007 and overall project completion is now set for April
2008.
|
|
| Site Work:
-
Continuing with removal of excess soil.
-
Portions of the main entrance road have received base pavement.
-
Work on Chain Bridge Road (Route 123) is expected to begin next
month.
|
|
| Lower Level:
-
Mechanical, electrical, plumbing rough-ins continue.
-
Duct testing continues.
-
Insulation is starting.
-
Air Handler testing has begun.
First Floor:
-
Stair installation is in process with five of the six stairs
complete.
-
Mechanical, electrical, plumbing work is in process.
-
Exterior brick veneer and precast is in process.
-
Perimeter framing has started.
-
Window installation has begun.
-
Stucco in the courtyard has started.
-
Front entrance tube steel and canopy have been installed.
Second Floor:
-
Door frames, metal stud walls and bulkheads are continuing.
-
Overhead mechanical, electrical, plumbing rough-ins work
continue.
-
Brick veneer and precast installation is on going.
| Third Floor:
-
Door frames, metal stud walls and bulkheads are continuing.
-
Overhead mechanical, electrical, plumbing rough-ins continue.
-
Brick veneer and precast installation is on going.
Fourth Floor:
-
Mechanical, electrical, plumbing rough-in work continue.
-
Curbs, air handling unit pads and screen wall structure are in
place.
-
Air handling units three and 11 have been set.
-
Standing Seam roofing at the courtroom pop-ups is nearing
completion.
-
Exterior masonry is complete.
-
Roofing work has resumed.
Fifth Floor:
-
Mechanical, electrical, plumbing rough-in work continue.
-
White brick installation is complete.
-
Stud walls have started.
Roof Level:
-
Work is ongoing in the elevator machine rooms.
|