Progress Photos - November 2006
Important News and Information
|
|
| General:
-
Overall Project is 61 percent complete.
-
The expansion is expected to receive substantial completion in
April 2007 and overall project completion is expected in April
2008.
Site Work:
-
Removal of excess soil continues.
-
Portions of the main entrance road have received base pavement.
-
Work on Route 123 is expected to begin next month.
|
|
| Lower Level:
-
Mechanical, electrical, plumbing work continues.
-
Access flooring installation in the Data/Telecom Room has
started.
First Floor:
-
Stair installation is in process with five of the six stairs
complete.
-
Mechanical, electrical, plumbing work is in progress.
-
Exterior brick at the columns is underway.
-
Perimeter framing has started.
-
Window installation is underway.
-
Stucco in the courtyard is ongoing.
-
Front entrance tube steel and canopy have been installed.
-
Elevators are being finalized.
Second Floor:
-
Door frames, metal stud walls and bulkheads are being finished.
-
Overhead mechanical, electrical, plumbing rough-ins continue.
-
Brick veneer and precast installation is ongoing.
-
Close-in of toilet rooms is in progress.
| Third Floor:
-
Door frames, metal stud walls and bulkheads are continuing.
-
Overhead mechanical, electrical, plumbing rough-ins continue.
-
Brick veneer and precast installation is ongoing.
-
Electric risers to the third floor have been energized.
Fourth Floor:
-
Overhead mechanical, electrical, plumbing rough-ins continue.
-
Curbs, air handling unit pads and screen wall structure are in
place.
-
Roofing work has resumed.
Fifth Floor:
-
Overhead mechanical, electrical, plumbing rough-ins continue.
-
Stud walls have been started.
Roof Level:
-
Work is ongoing in the elevator machine rooms.
|