Progress Photos - December 2006
Important News and Information
|
|
| General:
-
Overall Project is 62 percent complete.
-
The expansion is expected to receive substantial completion in
April 2007 and overall project completion is expected in April
2008.
-
Work in the south penthouse of the Jennings Building has begun
with the removal and replacement of four air handling units.
Site Work:
-
Roadwork on Judicial Drive and Chain Bridge Road is underway.
-
Sanitary Sewer work on Main Street is ready to start.
Exterior Work:
-
Arches at the southeast arcade have started.
-
Precast setting continue.
-
Caulking and window installation continue.
-
Courtyard stucco is ongoing.
|
|
| Lower Level:
-
Boiler startup occurred. All boilers will be up and running
within one month.
-
Access flooring installed in the Data/Telecom Room.
First Floor:
-
All six stairs are complete.
-
Temperature and humidity is being monitored in the large traffic
courtroom.
-
Elevator #7 is operational and in use.
Second Floor:
-
Wall close-in is underway.
-
Primer painting has begun.
-
Ceiling grid placement has begun.
| Third Floor:
-
Overhead mechanical, electrical, plumbing rough-ins continue.
-
Stud walls are underway.
Fourth Floor:
-
Overhead mechanical, electrical, plumbing rough-ins continue.
-
Stud walls are underway.
-
Standing seam roofing is nearing completion.
-
Roofing work is nearly complete.
Fifth Floor:
-
Overhead mechanical, electrical, plumbing rough-ins continue.
-
Stud walls are underway.
|