Progress Photos - January 2007
Important News and Information
|
|
| General:
-
Overall project is 63 percent complete.
-
The expansion is expected to receive substantial completion in
August 2007 and overall project completion is expected in April
2008.
-
Work in the south penthouse of the Jennings Building is ongoing.
The four air handlers have been replaced and nearing completion
to come back online.
Site Work:
-
Roadwork on Judicial Drive and Chain Bridge Road is ongoing.
-
Utility work lined up for early February.
-
Sanitary sewer work on Main Street is ongoing. Line across Main
Street is complete.
Exterior Work:
-
First set of arches at the southeast arcade are complete. The
middle section is underway.
-
Window and storefront installation are ongoing.
-
Courtyard stucco is ongoing.
-
Courtyard grading, walkways, lights and irrigation system are in
process as weather permits.
-
Two air handlers are up and running.
|
|
| Lower Level:
-
Boiler startup occurred. All boilers are ready to operate.
-
Finish installation is ongoing in the Telecom/Data Room.
First Floor:
-
All six stairs are complete.
-
Temperature and humidity is being monitored in the large traffic
courtroom.
-
Finish paint is ongoing in the traffic courtroom.
-
Elevator #7 is operational and in use.
-
Hydro test in lobby is complete.
Second Floor:
-
Ceiling grid and light ficture installation is ongoing.
-
Tile in bathrooms is nearly complete.
-
Finish paint has started.
| Third Floor:
-
Overhead mechanical, electrical, plumbing rough-ins continue.
-
Stud walls are underway.
Fourth Floor:
-
Overhead mechanical, electrical, plumbing rough-ins continue.
-
Stud walls are underway.
Fifth Floor:
-
Overhead mechanical, electrical, plumbing rough-ins continue.
-
Stud walls are underway.
|