Progress Photos - February 2007
Important News and Information
|
|
| General:
-
Overall Project is 65 percent complete.
-
The expansion is expected to receive substantial completion in
August 2007 and overall project completion is expected in April
2008.
|
|
| Jennings Building:
-
Work in the south penthouse is ongoing. The four air handlers
have been replaced and nearing completion to be brought back
online.
-
Work is progressing to start in the west penthouse.
-
A major electrical power shutdown was held on Feb. 17 to begin
prep work for the switchgear replacement.
-
Asbestos abatement is on-going.
|
|
| Site Work:
-
Roadwork on Judicial Drive and Chain Bridge Road is ongoing.
-
Sanitary Sewer work on Main Street is ongoing. Line across Main
Street is complete.
| Exterior Work:
-
First set of arches at the southeast arcade is complete. The
middle section is underway.
-
Window and storefront installation is ongoing.
-
Courtyard stucco is ongoing.
-
Courtyard grading, walkways, lights and irrigation system is in
process as weather permits.
|
|
| Lower Level:
-
Boiler startup occurred and all boilers are operational.
-
Finish installation is on-going in the Data/Telecom Room.
First Floor:
-
Temperature and humidity is being monitored in the large traffic
courtroom.
-
Millwork for the traffic courtroom has been delivered and
installation has begun.
-
Elevator #7 is operational and in use.
Second Floor:
-
Ceiling grid and light fixture installation is ongoing.
-
Tile in bathrooms is nearly complete.
-
Finish paint is ongoing.
-
Tile wainscot has begun.
| Third Floor:
-
Overhead mechanical, electrical, plumbing rough-ins continue.
-
Stud walls are underway.
-
Tile in bathrooms is beginning.
Fourth Floor:
-
Overhead mechanical, electrical, plumbing rough-ins continue.
-
Stud walls are underway.
Fifth Floor:
-
Overhead mechanical, electrical, plumbing rough-ins continue.
-
Stud walls are underway.
|