Progress Photos - March 2007
Important News and Information
|
|
| General:
-
Overall Project is 68 percent complete.
-
The expansion is expected to receive substantial completion in
August 2007 and overall project completion is expected in April
2008.
|
|
|
Jennings Building:
-
Work in the south penthouse is nearly complete.
-
Work has started in the west penthouse.
-
Asbestos abatement is ongoing.
-
Electrical riser installation is getting ready to start.
|
|
|
Site Work:
-
Roadwork on Judicial Drive and Chain Bridge Road is ongoing.
-
Gas lights and serpentine wall are in progress.
-
Sanitary sewer work on Main Street is nearly complete.
| Exterior Work:
-
East arcade arches are complete.
-
Window and storefront installation is ongoing.
-
Courtyard stucco is complete.
-
Courtyard grading, walkways, lights and irrigation system is in
progress.
|
|
| Lower Level:
-
Boiler startup occurred and air handling units are
operational.
-
Finish installation is on-going in the Data/Telecom Room.
First Floor:
-
Temperature and humidity is being monitored in the large traffic
courtroom.
-
Millwork for the traffic courtroom is installed.
-
Elevator #2 is operational and in use.
Second Floor:
-
Criminal courtroom millwork is being installed.
-
Temperature and humidity is being monitored.
-
Ceiling grid and light fixture installation is ongoing.
-
Tile in bathrooms is complete.
-
Finish paint is ongoing.
-
Tile wainscot is nearly complete.
| Third Floor:
-
Overhead mechanical, electrical, plumbing rough-ins continue.
-
Stud walls are underway.
-
Tile in bathrooms is nearly complete.
Fourth Floor:
-
Overhead mechanical, electrical, plumbing rough-ins continue.
-
Stud walls are underway.
Fifth Floor:
-
Overhead mechanical, electrical, plumbing rough-ins continue.
-
Stud walls are underway.
|