Overall Project is 70 percent complete.
-
The expansion is running a few months behind schedule. An
overall completion schedule is expected from the general
contractor in May 2007.
|
|
|
Jennings Building:
-
Work in the south penthouse is complete.
-
Work has started in the west penthouse.
-
Asbestos abatement is ongoing.
-
Electrical riser installation is underway.
|
|
|
Site Work:
-
Roadwork on Judicial Drive and Chain Bridge Road is ongoing.
-
Gas lights and serpentine wall are in progress.
-
Sanitary Sewer work on Main Street is complete.
|
Exterior Work:
-
North arcade arches are in progress.
-
Window and storefront installation is nearly complete.
-
Courtyard stucco is complete.
-
Courtyard grading, walkways, lights and irrigation system is in
progress.
|
|
|
Lower Level:
-
Boiler, chillers, and air handlers are operational.
-
Finish installation is ongoing in the Data/Telecom Room.
First Floor:
-
Temperature and humidity is being monitored in the large traffic
courtroom.
-
Millwork for the traffic courtroom is installed.
-
Elevator #2 is operational and in use.
Second Floor:
-
Criminal courtroom millwork is being installed.
-
Temperature and humidity is being monitored.
-
Ceiling grid and light fixture installation is ongoing.
-
Tile in bathrooms is complete.
-
Finish paint is ongoing.
-
Tile wainscot is nearly complete.
|
Third Floor:
-
Overhead mechanical, electrical, plumbing rough-ins continue.
-
Stud walls and drywall installation is underway.
-
Tile in bathrooms is complete.
Fourth Floor:
-
Overhead mechanical, electrical, plumbing rough-ins continue.
-
Stud walls are underway.
Fifth Floor:
-
Overhead mechanical, electrical, plumbing rough-ins continue.
-
Stud walls are underway.
|