Progress Photos - May 2007
Important News and Information
|
|
| General:
-
Overall Project is 72 percent complete.
-
The expansion is running a few months behind schedule. The
expansion is expected to have a phased completion beginning in
July with the second floor and finishing in late November.
Based on this schedule, it is anticipated that moves into
the expansion could begin in January 2008.
|
|
|
Jennings Building:
-
Work in the west penthouse is complete.
-
Asbestos abatement is ongoing.
-
Electrical riser installation is underway.
|
|
|
Site Work:
-
Roadwork on Judicial Drive and Chain Bridge Road is ongoing.
-
Gas lights and serpentine wall are in progress.
Lower Level:
-
Finish installation is ongoing in the Data/Telecom Room.
First Floor:
-
Temperature and humidity is being monitored in the large traffic
courtroom.
-
Millwork for the traffic courtroom is installed.
-
Spectator seating has been installed.
-
Fabric wall panels have been installed.
Second Floor:
-
Criminal courtroom millwork is being installed.
-
Temperature and humidity is being monitored.
-
Spectator seating has been installed.
-
Fabric wall panel installation has begun.
-
Carpet installation is ongoing.
-
Wood doors are being installed.
|
Exterior Work:
-
North arcade arches are nearly complete.
-
Window and storefront installation is nearly complete.
-
Courtyard grading, walkways, lights and irrigation system is in
progress.
Third Floor:
-
Overhead mechanical, electrical, plumbing rough-ins continue.
-
Stud walls and drywall installation is underway.
-
Tile in bathrooms is complete.
-
Ceiling grid and lights are being installed.
Fourth Floor:
-
Overhead mechanical, electrical, plumbing rough-ins continue.
-
Stud walls are underway.
Fifth Floor:
-
Overhead mechanical, electrical, plumbing rough-ins continue.
-
Stud walls are underway.
|