Progress Photos - June 2007


Important News and Information

  General:
  • Overall Project is 74 percent complete.
  • The expansion is running a few months behind schedule.  The expansion is expected to have a phased completion beginning in July with the second floor and finishing in late December 2007.  Based on this schedule, it is anticipated that moves into the expansion could begin in January 2008.
 

Jennings Building:

  • Work in the west penthouse is complete.
  • Asbestos abatement is ongoing.
  • Electrical riser installation is underway.
 

Site Work:

  • Roadwork on Judicial Drive and Chain Bridge Road is ongoing.
  • Gas lights and serpentine wall are in progress.

Lower Level:

  • Finish installation is ongoing in the Data/Telecom Room.

First Floor:

  • Temperature and humidity is being monitored in the large traffic courtroom.
  • Millwork for the traffic courtroom is installed.
  • Spectator seating has been installed.
  • Fabric wall panels have been installed.
  • Drywall partition, electrical and mechanical work is proceeding.

Second Floor:

  • Criminal courtroom millwork is installed.
  • Temperature and humidity is being monitored.
  • Spectator seating has been installed.
  • Fabric wall panel installation has begun.
  • Carpet installation is ongoing.
  • Wood doors are being installed.
  • Wall tile and paint are in progress.
  • Ceiling grid and tile installation are in progress.
  • Bathroom finishes are in progress.

Exterior Work:

  • North arcade arches are complete.
  • Window and storefront installation is nearly complete.
  • Courtyard grading, walkways, lights and irrigation system are in process.

Third Floor:

  • Overhead mechanical, electrical, plumbing rough-ins continue.
  • Stud walls and drywall installation is underway.
  • Tile in bathrooms is complete.
  • Ceiling grid and lights are being installed.

Fourth Floor:

  • Overhead mechanical, electrical, plumbing rough-ins continue.
  • Stud walls and drywall installation is underway.

Fifth Floor:

  • Overhead mechanical, electrical, plumbing rough-ins continue.
  • Stud walls and drywall installation is underway.

Progress Photos

pic1pic2pic3
pic4pic5pic6
pic7pic8pic9
pic10pic11pic12
pic13pic14pic15
pic16    


Previous MonthNext Month
Courthouse Expansion Home




Contact Us: General (Office of Public Affairs) | Technical (Web Administrator) | Directed Inquiries (County Agencies)
Phone: County Main Number - 703-FAIRFAX (703-324-7329), TTY 711 | County Phone Listing

ADA Accessibility | Website Accessibility
Awards | FOIA | Mobile | Using this Site | Web Disclaimer & Privacy Policy | Get Adobe Reader
Official site of the County of Fairfax, Virginia, © Copyright 2011
Verizon Cybertrust Security Certified Logo;

Website Survey Website Survey    Globe with various flags representing Web site language translations   Language Translations

Return to Graphic Version