Progress Photos - August 2007
Important News and Information
|
|
| General:
-
Overall Project is 78 percent complete.
-
The expansion is running a few months behind schedule. The
expansion is expected to have a phased completion beginning with
the second floor and finishing in late December 2007 with an
occupancy permit in late January 2008. Based on this schedule, it
is anticipated that moves into the expansion could begin in
February 2008.
|
|
|
Jennings Building:
-
Work in the west penthouse is complete.
-
Electrical riser installation is underway.
|
|
|
Site Work:
-
Roadwork on Judicial Drive and Chain Bridge Road is ongoing.
-
Gas lights are complete.
-
Brick sidewalks are in progress.
-
Serpentine wall is complete.
Lower Level:
-
Finish installation is ongoing in the Data/Telecom Room.
First Floor:
-
Large traffic courtroom is complete.
-
Drywall partition, electrical, and mechanical work is proceeding.
-
Wall tile has started.
-
Painting has started.
Second Floor:
-
Substantial completion reached on this floor on July 24, 2007.
|
Exterior Work:
-
Building masonry is complete.
-
Window and storefront installation is about 90 percent complete.
-
Courtyard grading, walkways, lights and irrigation system are in
progress.
Third Floor:
-
Overhead mechanical, electrical, plumbing rough-ins continue.
-
Ceiling grid and lights are being installed.
-
Courtroom millwork is in progress.
-
Wall tile and painting is in progress.
-
Casework in agency spaces is in progress.
Fourth Floor:
-
Mechanical, electrical, plumbing rough-ins continue.
-
Stud walls and drywall installation is underway.
Fifth Floor:
-
Mechanical, electrical, plumbing rough-ins continue.
-
Stud walls and drywall installation is underway.
|