Progress Photos - October 2007
Important News and Information
|
|
| General:
-
Overall Project is 80 percent complete.
-
The expansion is expected to have a phased completion beginning
in July with the second floor and finishing in late December 2007
with an occupancy permit in late January 2008. Based on this
schedule it is anticipated that moves into the expansion could
begin in late February or early March 2008.
|
|
|
Jennings Building:
-
Electrical riser installation is underway.
|
|
|
Site Work:
-
Roadwork on Judicial Drive and Chain Bridge Road is on-going.
-
Gas lights and serpentine wall are complete.
-
Brick sidewalks are complete.
-
Serpentine wall is complete.
-
Landscaping has begun.
Lower Level:
-
Finish installation is on-going in the Data/Telecom Room.
First Floor:
-
Substantial completion reached on this floor on Oct. 31, 2007.
Second Floor:
-
Substantial Completion reached on this floor on July 24, 2007.
|
Exterior Work:
-
Building masonry is complete.
-
Window and storefront installation is 100 percent complete.
-
Courtyard grading, walkways, lights and irrigation system are
complete.
Third Floor:
-
Substantial completion reached on this floor on Sept. 30, 2007.
Fourth Floor:
-
Painting is underway.
-
Ceilings and light fixtures are finishing.
-
Carpet installation is in progress.
-
Courtroom millwork is in progress.
Fifth Floor:
-
Overhead mechanical, electrical, plumbing rough-ins continue.
-
Stud walls and drywall installation is underway.
|