Foundation and Footing Permits
The Permit Application Center will accept plans for a footing and foundation permit, provided the project has been approved for Modified Processing and a Rough Grading Plan and a full Site Plan have been submitted. The following items must be addressed:
-
A copy of the letter approving the project for modified processing
review must be attached to each set of plans.
-
Three sets of plans must be submitted, including site plans,
architectural and structural details, in order to review the size of
the building as well as the structural adequacy of the footings.
-
An additional set of plans must be submitted for those projects that
will request letters of extension to proceed with construction prior to
issuance of a full building permit.
-
At least one set of full architectural plans must be submitted with the
footing and foundation plans so that a technician can determine the
inspectable areas for the entire building and assess the fees
accordingly.
-
One copy of a soil test report must be submitted with the footing and
foundation plans.
-
If the footing and foundation plans include plumbing, mechanical and
electrical drawings, they must be in sufficient detail to allow review
of the entire building system so that the associated underground work
can proceed with the footing and foundation permit.
-
The plans and the permit application must clearly state what work is
included in the permit set. For example, plumbing, mechanical and
electrical work must be shown if the associated trade permits are to be
obtained after the footing and foundation permit is issued.
-
The customer will pay a filing fee for the footing and foundation
permit based on thirty-five percent of the full building fee.
-
Prior to issuance of a footing and foundation permit, the entire
building fee and a minimum fixture unit fee must be paid.
-
At the present time the minimum fixture unit fee is based on thirty
fixture units. The fixture unit fee must be paid to the Wastewater
Planning and Monitoring Division (and the permit application approved)
prior to issuance of the footing and foundation permit.
-
When the full building permit package is filed the customer will be
assessed a minimum building fee.
-
Prior to issuance of the full building permit, the total fixture unit
fees must be paid and the application approved by the Department of
Public Works and Environmental Services, Wastewater Planning and
Monitoring Division located at 12000 Government Center Parkway, Suite
358, Fairfax, Virginia 22035.
-
For further information on fees, contact the Permit Application Center
at 703-222-0801, TTY 711.
-
The footing and foundation permit will be issued after all of the plans
and the permit application have been approved.
-
A meeting must be held prior to permit issuance for all projects
requiring special inspections.
-
For further information on the Special Inspections Program, formerly
called the Critical Structures Program, please call
703-324-1060, TTY 711.
- If the building is in a problem soil area as designated by the Fairfax County soils map, the soils report must be approved by the Geotechnical Section of the Site Development and Inspections Division, prior to issuance of the permit. The Geotechnical Section may be contacted at 703-324-1720, TTY 711.