Construction Progress April 2007


Important News and Information

 

Building Construction:

  • The Public Safety and Transportation Operations Center (PSTOC) project is 30% complete, and is currently on schedule and within budget.
  • The critical path for construction scheduling includes completion of the structure as well as both building envelopes. This path anticipates that once the PSTOC structure and envelope are complete, the contractor will move to the Forensics building to complete the same tasks.
  • Structural steel erection on the PSTOC portion of the facility is nearing completion. Structural steel erection is expected to begin at the Forensics facility in mid-May.
  • The structural truss at the facility's front entry was successfully set in place in mid-April.
  • Infrastructure for the communication monopole antenna continued.
  • Concrete curb and gutter installation at the visitor and employee parking lots has been completed.
  • Installation of precast concrete panels and the facility's exterior walls is also scheduled to begin in May.

Progress Photos

April 2007 Facility and Parking
Facility/Parking View 1
April 2007 Northeast View
Northeast View 2
April 2007 Northwest View
Northwest View 3
April 2007 PSTOC View
View 4
April 2007 South View
South View 5
April 2007 Southeast View
Southeast View 6

 

Previous Month  | Next Month
Poject Home


Contact Fairfax County: Phone, Email or Twitter | Main Address: 12000 Government Center Parkway, Fairfax, VA 22035
Technical Questions: Web Administrator

ADA Accessibility | Website Accessibility
Awards | FOIA | Mobile | Using this Site | Web Disclaimer & Privacy Policy | Get Adobe Reader
Official site of the County of Fairfax, Virginia, © Copyright 2013

Website Feedback Website Feedback    Globe with various flags representing Web site language translations   Language Translations

Return to Graphic Version