Construction Progress April 2008
Important News and Information
|
|
|
Building Construction:
-
The collaboration, planning, and communication of the McConnell
Public Safety and Transportation Operations Center (MPSTOC)
partners continue, and have resulted in a project that is 95%
complete, on schedule, and within budget.
-
PSTOC Facility:
-
Interior finishes are complete in some areas.
-
Close in of ceilings is nearing completion.
-
Terrazzo and resilient flooring is finished.
-
Carpet has been installed in all areas except the raised
access floor areas.
-
Systems furniture has been installed in the second level
rooms and is in progress on the first level.
-
Consoles in the command center will be installed starting in
May.
-
The electrical system including the emergency generators is
installed and being tested.
-
Additional panels and circuits for user equipment will be
installed in May.
-
Start up of the HVAC systems is in progress.
-
The monopole for antennas has been erected.
-
Landscaping of the courtyard is nearing completion.
Forensics Facility:
-
Interior finishes, ceiling tiles, and carpeting are in
progress.
-
Resilient and epoxy flooring have been completed.
-
Installation of millwork, laboratory fixtures, and equipment
is nearly complete.
-
Paving of the service yard is complete and installation of
the security gates is in progress.
-
Systems furniture will be installed in May.
|
Progress Photos
|
East View
|
South View
|
North View
|