Construction Progress May 2008
Important News and Information
|
|
|
Building Construction:
-
The collaboration, planning, and communication of the McConnell
Public Safety and Transportation Operations Center (MPSTOC)
partners continue, and have resulted in a project that is 96%
complete, on schedule, and within budget. The PSTOC building,
along with the Forensics building, is scheduled to be complete at
the end of July.
-
PSTOC Facility:
-
The building, the two story connector to the Forensics
building, and the landscaping around the building are nearing
completion.
-
The balance of site work at the entrances and security gates
will be completed in June. Installation of 94 consoles for
the communications center was added to the project.
-
Audio visual, information systems, and communications
equipment rooms have been completed, checked, secured for use
by equipment installation contractors.
-
Completion checks of office areas have started.
-
Systems furniture has been installed on both levels and a
completion list developed.
-
About half of the consoles in the command center are
installed with the balance on schedule to be complete in
early July.
-
The first permanent power feed was energized in November.
-
The electrical system including the emergency generators is
installed and being tested.
-
Some of the HVAC equipment is operating to control the
building temperature and humidity.
-
Commissioning tasks are in progress.
Forensics Facility:
-
Interior finishes, ceiling tiles, and carpeting are in
progress.
-
Resilient and epoxy flooring have been completed.
-
Installation of millwork, laboratory fixtures, and equipment
is complete.
-
Interior finishes are on schedule for completion in July.
-
Ceiling close in is in progress.
-
Systems furniture has been installed and completion checks
made.
|
Progress Photos
|
North View
|
South View
|
Southeast View
|