Construction Progress July/August 2008
Important News and Information
|
|
|
Building Construction:
-
The collaboration, planning, and communication of the McConnell
Public Safety and Transportation Operations Center (MPSTOC)
partners continue, and have resulted in a project that is 100%
complete, on schedule, and under budget. The PSTOC building,
along with the Forensics building, reached substantial completion
on July 31, 2008.
-
PSTOC Facility:
-
The Occupancy Permit for the McConnell PSTOC Building and the
Forensic Facility was obtained ahead of schedule on July 30,
2008.
-
A Notice-of-Substantial Completion was issued to the General
Contractor on July 31, 2008.
-
The General Contractor is currently completing punch lists
and working on warranty items.
-
Commissioning of the HVAC system with summer trend data is in
progress.
-
The 94 consoles for the communications center which were
added to the project have been completed.
-
Audio visual, information systems, and communications
equipment is being installed by the Fairfax County
contractors.
-
Systems furniture installation has been completed in all
areas.
-
Testing by the utility will be completed in early September.
-
Several agencies have moved into the building which is being
managed by the Building General Manager and maintained by
FMD.
Forensics Facility:
-
The General Contractor is currently completing the punch-list
items.
-
Systems furniture has been installed.
-
Modifications needed for the computer room have been
completed.
-
Some Police Department personnel have moved into the
building.
|