Construction Progress October - November 2006


Important News and Information

 

Building Construction:

  • The building site has been stabilized by putting in a silt pond and super silt fences to ensure that there would be little to no silt or erosion issues.
  • A substantial portion of the asphalt parking area has been installed.
  • Curbs, gutter and onsite utilities including stormwater sewer, sanitary sewers and waterlines are in place.
  • Limited landscaping and screening with newly planted trees has been started.
  • Footings and foundations are approximately 50 percent complete.
  • In December, the footings and foundations are projected to be complete, and the contractor will begin pouring the first floor concrete slab.

Progress Photo's

October 2006 view 1
October 2006
October 2006 view 2
October 2006
Mid November 2006 view 1
Mid-November 2006
Mid November 2006 view 2
Mid-November 2006
November 2006 view 1
November 2006
November 2006 view 2
November 2006
November 2006 view 3
November 2006
November 2006 view 4
November 2006


Previous Month | Next Month
Project Home



Contact Fairfax County: Phone, Email or Twitter | Main Address: 12000 Government Center Parkway, Fairfax, VA 22035
Technical Questions: Web Administrator

ADA Accessibility | Website Accessibility
Awards | FOIA | Mobile | Using this Site | Web Disclaimer & Privacy Policy | Get Adobe Reader
Official site of the County of Fairfax, Virginia, © Copyright 2013

Website Feedback Website Feedback    Globe with various flags representing Web site language translations   Language Translations

Return to Graphic Version