Construction Progress December 2006 - January 2007


Important News and Information

 

Building Construction:

  • The base asphalt course was installed in October 2006 on the northeastern portion of the parking lot, providing a staging area and parking for the field offices of the contractor, and Department of Public Works and Environmental Services.
  • Construction of the building foundation, walls and slab-on-grade is approximately 70 percent complete.
  • The steel structure erection began in late January 2007 and is anticipated to continue for approximately four months.

Progress Photo's

December 2006 view 1
December 2006 View 1
December 2006 view 2
December 2006 View 2
December 2006 View 3
December 2006 View 3
January 2007 view 1
January 2007 view 1
January 2007 view 2
January 2007 view 2
January 2007 view 3
January 2007 view 3

 

Previous Month | Next Month
Project Home


Contact Fairfax County: Phone, Email or Twitter | Main Address: 12000 Government Center Parkway, Fairfax, VA 22035
Technical Questions: Web Administrator

ADA Accessibility | Website Accessibility
Awards | FOIA | Mobile | Using this Site | Web Disclaimer & Privacy Policy | Get Adobe Reader
Official site of the County of Fairfax, Virginia, © Copyright 2013

Website Feedback Website Feedback    Globe with various flags representing Web site language translations   Language Translations

Return to Graphic Version