Huntington Levee


Fairfax County is building a levee and pumping station to protect homes and other property in the Huntington neighborhood from flooding. Voters approved a $30 million stormwater bond in November 2012 to fund the construction of the levee and pumping station. This is a complicated project that has required review by local, state, and federal agencies. Completion is scheduled for spring 2019.

Huntington Levee Huntington Levee Huntington Levee Huntington Levee

Project Update: Jan. 19, 2017

Construction on the Huntington Levee has started on schedule. Archer Western, a general contractor from Atlanta, Georgia, was awarded the contract to build the levee. Mobilization and light construction activities have begun and will continue to ramp up in February. The project is scheduled to be completed by spring 2019, as long as the weather cooperates.

Two temporary trailers have been placed on-site to serve as offices for the contractor and engineering firm. For safety reasons, please stay away from the trailers. Safety fencing and signage will be erected soon closing access to the park. Erosion and sediment controls (black, cloth fencing) will be installed next. An access road will be built from Metroview Parkway on the eastern border of the site. Most construction vehicles will access the site via this entrance. Maps and renderings were presented at the Oct. 22, 2016 community meeting.

What to Expect During Construction

  • Construction activities will be limited to 7 a.m. to 7 p.m., Monday through Friday.
  • Any weekend and/or holiday work must first be approved by the county.
  • Contractor parking is prohibited in the neighborhood.
  • Truck traffic through the neighborhood will be restricted.
  • Noise levels will comply with the Fairfax County Noise Ordinance.
Huntington Levee

Parks Update

The Huntington Park playground and surrounding green space is closed and will be secured with perimeter fencing. Improvements to Farrington Park playground are scheduled to begin in February and should be completed spring 2017. Once the levee project is completed in 2019, residents will have approximately 4,800 linear feet of recreational trails along the top of the levee and around the ponding area.

Contact Information

For general questions about the project, call 703-324-5800, TTY 711, or send email to HuntingtonLevee@fairfaxcounty.gov. To report construction-related concerns during regular business hours (Monday-Friday, 7:30 a.m. to 4 p.m.), call 703-324-5800, TTY 711. For after-hours concerns related to construction activities contact the Project Engineer at 571-344-4615. For rising water that threatens your safety, call 9-1-1. To report storm flooding during regular business hours (Monday-Friday, 7:30 a.m. to 4 p.m.), call 703-877-2800, TTY 711. For after-hours storm flooding emergencies that are not life threatening, call 703-323-1211, TTY 703-239-8498, and state that you are reporting a storm sewer emergency. For sanitary sewer flooding, call 703-323-1211, TTY 703-239-8498. Report suspicious activities to the public safety non-emergency line at 703-691-2131, TTY 703-204-2264.

Project Need

The Huntington community floods due to tidal surges from the Potomac River and flash flooding from the Cameron Run Watershed. The community was built prior to enactment of the current floodplain regulations.

Since 2002, three floods have damaged vehicles and other property in this neighborhood. There are 160 homes in the FEMA-designated floodplain that are at risk in the future.

While the levee can prevent flooding of houses from the types of storms that have happened in the past, it is not designed to offer protection from flooding that is caused by storms that are greater than a 100-year event (a storm that has a one percent chance of occurring in a given year).

Huntington Levee

Click for larger image

A temporary fence will be erected along the perimeter of the site (yellow line) and remain in place until the completion of the project in 2019.

Receive email notification of public meetings and project updates:


You will be sent a subscription confirmation request which you must reply to with the word OK as the body of the message. (The message that is sent will also have instructions letting you know how to respond.)



Project Description

The levee will run parallel to Cameron Run. The purpose of a constructed levee is to minimize flooding, however street flooding may still occur during extreme events.

The design prepared by ARCADIS includes:

  • Levee - Earthen embankment and I-wall combination
    • 2,800 feet long (beginning west of Fenwick Drive and running eastward to the Riverside apartments)
    • 6 to 11-foot high earthen embankment (height is dependent upon the elevation of the existing ground along the alignment of the levee)
    • 4-foot high concrete I-wall on top of the earthen embankment
    • 13 feet wide at the top of the embankment including an 8-foot wide asphalt trail
    • Average of 43 to 68 feet wide at the base, dependent upon the height of the levee
    • Buried collection drain along the toe of the levee to control ground water seepage
    • New storm drains to connect existing storm drains to the pump station
    • Concrete box culverts and a vegetated swale will divert stormwater from the to the pumping station during large storm events
  • Pumping station facility, located near the east end of the levee

While the levee can help mitigate flooding of houses from the types of storms that have happened in the past, it is not designed to offer protection from flooding that is caused by storms that are greater than a 100-year event (a storm that has a one percent chance of occurring in any given year). 

Project Complexities

The levee design has been a complex process that required:

  • Permits from local, state and federal agencies (all permit requirements have been met)
  • Environmental and other reviews by state and federal agencies
  • Construction in a wetlands, which is regulated by state and federal agencies
  • Acquisition of land and easements
  • Relocation of existing utilities

Project Timeline

The levee design and contract award were completed on schedule.

The county is proceeding on the following schedule:

  • Project Design Phase I (June 2013 – January 2014) - Completed
    • Data Collection
    • Site Study
    • Conceptual Design

  • Project Design Phase II (January 2014 - Winter 2017) - Completed
    • Schematic Design
    • Design Development
    • Construction Documents
    • Permitting
    • Land Acquisition
    • Bidding

  • Construction (Winter 2017 - Spring 2019)

For more information or to submit questions or comments about the Huntington Levee project, please call 703-324-5800, TTY 711, or email huntingtonlevee@fairfaxcounty.gov.


Contact Fairfax County: Phone, Email or Twitter | Main Address: 12000 Government Center Parkway, Fairfax, VA 22035
Technical Questions: Web Administrator

ADA Accessibility | Website Accessibility
Awards | FOIA | Mobile | Using this Site | Web Disclaimer & Privacy Policy | Get Adobe Reader
Official site of the County of Fairfax, Virginia, © Copyright 2017

Website Feedback Website Feedback    Globe with various flags representing Web site language translations   Language Translations

Return to Graphic Version