An overview of Fairfax County, Virginias Special Permit Process, from the time an application is filed, to the time of the Board of Supervisors Public Hearing (90 days).
-
Application is filed by the Applicant.
-
Application submissions are reviewed. when all Zoning Ordinance submission requirements are met, applications are accepted (start of the 90 day process).
-
Application is scheduled for public hearing, is assigned to a staff coordinator, and distributed to various county agencies.
-
Prestaffing of application. Applicant contacted by staff about initial staff comments.
-
Revisions relating to prestaffing comments are submitted.
-
Staffing of application/Applicant will be contacted by staff about final staff comments.
-
Revisions relating to the staffing comments are submitted.
-
Notification to adjacent property owners (sent to Applicant 40 days prior to hearing, notices mailed by Applicant postmarked at least 15 days prior to hearing).
-
Final submission deadline (5 weeks prior to Board of Zoning Appeals Public Hearing. Staff report is published based on information received by this date).
-
Staff report published (1 week prior to public hearing).
-
Board of Zoning Appeals Public Hearing.
|