Construction for the North County Government Center will be done in phases over the next 22 months.  Supervisor Hudgins' office and the Reston Police Station will move into the new building Summer 2014.   Following is a projected timeline for the completion of each phase:

  • Phase 1:  Contractor mobilization and site work
    • Complete Summer 2013
  • Phase 2:  Construct new building for Reston Police Station and Hunter Mill Supervisor's Office
    • Complete Summer 2014
  • Phase 3:  Demolish existing building, construct public parking lot and new fuel station
    • Complete Fall 2014
  • Phase 4:  Construct remainder of secure police parking lot
    • Complete Winter 2014.

Parking in the North County Governmental Center lot will be limited during the construction period, however, street parking will remain available.

Questions?  Please contact the Hunter Mill District Office.  

CHECK OUT THE CONSTRUCTION PROGRESS:   

MAY 2013:  Dirt hill next to front parking and utilities start going in.

dirt hill ground work

AUGUST 2013: Walls begin!

August progress

October 2013:  The Big Crane work

October progress

 

 


Contact Fairfax County: Phone, Email or Twitter | Main Address: 12000 Government Center Parkway, Fairfax, VA 22035
Technical Questions: Web Administrator

ADA Accessibility | Website Accessibility
Awards | FOIA | Mobile | Using this Site | Web Disclaimer & Privacy Policy | Get Adobe Reader
Official site of the County of Fairfax, Virginia, © Copyright 2013

Website Feedback Website Feedback    Globe with various flags representing Web site language translations   Language Translations

Return to Graphic Version