Monument Drive Commuter Parking Garage and Transit Center
2022-12-09T07:00:00
2022-12-09T07:00:00
Estimated Completion: End of 2023
Funding: $40,850,000 Funding has been provided by the VDOT I-66 Concessions funds.
Architect: HGA
Contractor: Howard Shockey & Sons, Inc.
Project Manager: Ipek Aktuglu
Project Engineer: Padam Sethi
KEY FEATURES: 820-space parking garage, 8-bus bay transit center with glass and steel canopy over the bus bays, a short-term parking area for pick up and drop off, commuter (slug) lanes, secure bicycle parking and storage, bicycle racks, solar panels to reduce energy consumption, and a partial green roof.