EMTA Maintenance Facility (0047WP) Pond Improvement Plan - Construction Summary
Public Works and Environmental Services Alert:
CONTACT INFORMATION:
Our administrative offices are open to the public. Appointments are preferred. Please call or email 8 a.m. - 4:30 p.m., Monday – Friday
EMTA Maintenance Facility (0047WP) Pond Improvement Plan - Construction Summary
2023-08-22T11:00:00
2023-08-22T11:00:00
Project No. – SD-000033-081
Project Engineer – Tesfu Medhin
Contractor – Triangle Contracting, LLC
Location – Springfield District
Scope - Project consists of wet dredging an existing wet pond and repairing several stormwater outfalls. The work includes the following: dredging of approximately 2,315 cubic yards of sediment, tree removal, stormwater pipe outfall repair and concrete curb cut and channel.