Raw Wastewater Pumping System Rehabilitation/Replacement-B3 - Construction Summary

 
  • Project No. WW-000009-012
  • Engineer – Biniam Habtom
  • B3 Rehabilitation consisting of demolition of existing 6” header and wall cleaning system on EQ Tanks No. 1-4, demolition of WWR Pumps and above grade WWR piping in Tanks No. 1-5, replacement of sump pumps and valves in the existing valve vaults, replacement of 1-ton crane, installation of Odor Control System in Tank No. 1, installation of aluminum cover for Tank No. 1
  • Location: Mount Vernon District
  • Anticipated Completion – Spring 2024
  • CMAR Contractor – Clark Construction Group, LLC