The project is currently under construction to install new culverts and construct a paved roadway from the cul de sac to the northern stream embankment. The roadway from the northern stream embankment to the driveway at 2600 Hickory Hollow Lane, will be an unpaved gravel roadway.
Project Background
The current culvert beneath Hickory Hollow Lane at Rocky Branch Stream, is severely undersized. Hickory Hollow Lane is owned and maintained by Fairfax County. During large rain events, the stream overtops the roadway, preventing safe access to the two residential properties located north of the crossing. Also, the overtopping water damages the roadway, resulting in regular maintenance operations and causes sediment to contaminate the waterway downstream from the crossing.
Project Description
Improve Hickory Hollow Lane to raise the roadway, install four culverts, pave the roadway with two 9-foot lanes and 6-foot shoulders at the stream crossing and install guardrail at the stream crossing. Beyond (north of) the stream crossing, the roadway section will consist of two 9-foot-wide paved travel lanes and 2-foot-wide gravel shoulders adjacent to each lane. This is the most minimal design allowed for this roadway. This work will convey Rocky Branch Stream under the newly constructed roadway and prevent the roadway from flooding and eroding during rain events. All improvements will be located within the County’s existing 50-foot-wide dedicated roadway. The purpose of this project is to prevent the roadway from being overtopped by the stream during heavy rain events, resulting in the roadway remaining passable to vehicles and reduce erosion of the roadway. This project will have no impact on Ashlawn Park, and this project is independent of the Rocky Branch at Hickory Hollow Lane Stream Restoration project.
Project Location
The project is located in the Providence District.
Project Benefits
Reduce the time the road is overtopped during flood events.
Bring the road into compliance with current regulations.
Prevent soil from eroding along the roadway and generating sediment downstream.
Reduce the need for County staff to repair the roadway after heavy rain events.
Facilitate snow removal operations.
Provide a smoother riding surface for users of the roadway.
Facilitate emergency vehicle access.
Replacement trees planted adjacent to the planned roadway.
Project Phase
The project is currently under construction to install new culverts and construct a paved roadway from the cul de sac to the northern stream embankment. The roadway from the northern stream embankment to the driveway at 2600 Hickory Hollow Lane, will be an unpaved gravel roadway.
Project Timeline
Construction of the roadway work is anticipated to be completed in the Spring of 2025.
What to Expect
The residents can expect construction noise during daytime hours, construction equipment moving along Hickory Hollow Lane and single lane traffic control. The contractor will seek a noise waiver to operate a pump at night. Work may occur during some weekends. Residents will have access to and from their homes at all times.
Project Cost and Funding Source
The estimated construction cost is approximately $1.5M. Funds are available from the roadway maintenance funds.
Supervisor Dalia Palchik hosts a meeting for DPWES to provide the latest updates, provide historical perspective, and respond to community and stakeholder questions about the project.