Pohick Road Pedestrian Improvements

Virtual Community Meeting Set for May 26, 2026

FCDOT hosted an online community information meeting on May 26, to provide an overview of the project purpose and need, proposed improvements, anticipated schedule and next steps. 

Provide feedback to the project team (comments accepted through June 10)

  • Online survey
  • Leave a recorded voice mail message for the project team at 703-890-5898, Project Code 6840

Project Description

The Pohick Road Pedestrian Improvements project (Project No. 1400171-25) is intended to enhance pedestrian connectivity and safety along the Pohick Road corridor between Route 1 and the I-95 Bridge.

Proposed improvements include:

  • Construction of a 10-foot-wide asphalt walkway with a minimum 4-foot buffer on the south/west side of Pohick Road between Larne Lane and Lorton Station Boulevard.
  • Relocation of the pedestrian signal crossing at the south leg of the Lorton Station Boulevard intersection to improve connectivity across the corridor.
  • Construction of a 7-foot-wide concrete walkway with at least a 4-foot buffer on the east/north side of Pohick Road between Lorton Station Boulevard and the I-95 Bridge.
  • Installation of curb and gutter where appropriate throughout the corridor.
  • View project plans

The corridor currently has a mix of segments with 4-foot sidewalks, an 8-foot paved trail and no pedestrian or bicycle facilities. 

Estimated project budget is $13 million.


 

Anticipated Project Schedule

  • Intermediate Design: Fall 2026
  • Pre-Final Design: Spring 2027
  • Final Design: Summer 2029
  • Land Acquisition: Fall 2029
  • Utility Relocation: Spring 2030
  • Notice to Proceed (Construction): Spring 2031
  • Construction Completion: Spring 2032 
     