Project Background
FCDOT is working to complete missing walkway segments on Crestview Drive between Ferris Avenue and Builders Road.
In addition to connecting the walkway, the project includes new curb and gutter on the western side of Crestview Drive, crosswalks and pedestrian signals, an 8' wide pedestrian refuge island and ADA ramps.
Project Number: 2G40-088-054
Project Schedule (Updated July 2025):
Intermediate Design (60% Design) |
Completed February 2025 |
Pre-Final Design (90% Design) |
November 2025 |
Land Acquisition |
February - October 2026 |
Begin Construction |
June 2027 |
Construction Completion |
March 2028 |