Project Background
FCDOT is working to complete missing walkway segments on Crestview Drive between Ferris Avenue and Builders Road.
In addition to connecting the walkway, the project includes new curb and gutter on the western side of Crestview Drive, crosswalks and pedestrian signals, an 8' wide pedestrian refuge island and ADA ramps.
Project Number: 2G40-088-054
Proposed Project Schedule:
60% Design |
February 2025 |
90% Design |
September 2026 |
Initiate Land Acquisition |
December 2025 - August 2026 |
Utility Relocation Completion |
December 2025 - August 2026 |
Begin Construction |
March 2027 |
Construction Completion |
October 2027 |