Project Background
FCDOT is working to complete missing walkway segments on Crestview Drive between Ferris Avenue and Builders Road.
In addition to connecting the walkway, the project includes new curb and gutter on the western side of Crestview Drive, crosswalks and pedestrian signals, an 8' wide pedestrian refuge island and ADA ramps.
Project Number: 2G40-088-054
Project Schedule (Updated May 2026): The project has moved into Pre-Final (90%) Design.
| Intermediate Design (60% Design) | Completed February 2025 |
| Pre-Final Design (90% Design) | May 2026 |
| Land Acquisition | August 2026 - April 2027 |
| Begin Construction | June 2027 |