Crestview Drive Walkway

Community Meeting Set for May 7, 2025

FCDOT will host a community meeting to discuss the design of the Crestview Drive Walkway project on Wednesday, May 7, 2025, at Clearview Elementary School, 12635 Builders Road, Herndon. The meeting will begin with an Open House at 6 p.m., a presentation and meeting at 7 p.m., and a Question and Answer session to follow.


Project Background

Crestview Drive Current Conditions ImageFCDOT is working to complete missing walkway segments on Crestview Drive between Ferris Avenue and Builders Road.

In addition to connecting the walkway, the project includes new curb and gutter on the western side of Crestview Drive, crosswalks and pedestrian signals, an 8' wide pedestrian refuge island and ADA ramps.

Project Number:  2G40-088-054

Proposed Project Schedule:

60% Design February 2025
90% Design September 2026
Initiate Land Acquisition December 2025 - August 2026
Utility Relocation Completion December 2025 - August 2026
Begin Construction  March 2027
Construction Completion   October 2027
Project Location

Crestview Drive Project Location Map

Questions? Comments?