Public Works and Environmental Services

CONTACT INFORMATION: Our administrative offices are open to the public. Appointments are preferred. Please call or email 8 a.m. - 4:30 p.m., Monday – Friday
703-324-5800 TTY 711
12000 Government Center Parkway
Suite 449 Fairfax, VA 22035
Carey Needham
Director, Capital Facilities

Rehabilitation of the Activated Sludge Effluent Pump Station - Construction Summary

 
  • Project No. – WW-000017-015
  • Engineer –Remon Morcos
  • Scope: Rehabilitation of the Activated Sludge Effluent (ASE) Pump Station which conveys secondary effluent to the Moving Bed Biological Reactor Facility process.
  • The work at the Activated Sludge Effluent Pump Station (ASE PS; Building BB) includes replacement of six vertical turbine pumps, replacement of seven cast-iron sluice gates and seven actuators and replacement of 14 valves and six actuators.
  • Location: Mount Vernon District
  • Anticipated Completion – Summer 2026
  • Contractor – Clark Construction Group, LLC

Add to calendar
Fairfax Virtual Assistant