Project Information
(Updated August 2025) Lee Chapel Road between Ox Road (Rt. 123) and Fairfax County Parkway is a minor arterial that is narrow, two-lane road with severe hills. Fairfax County is in the preliminary design phase of the project to remove the two vertical curves along a portion of Lee Chapel Road approximately between the bridge over South Run and the intersection of Pond Point Road. The project does not envision widening the road; the road will remain two lanes but will be brought up to current design standards. The proposed improvements will significantly improve roadway alignment and safety.
Schedule (Updated December 2025):
The Intermediate (60%) design plans have been submitted for VDOT and County review. The tentative project schedule includes:
- 90% Design Completion – Early Summer 2026
- Land Acquisition Begins – Winter 2026
- Land Acquisition Completion – Winter 2027/Spring 2028
- Utility Relocation – Fall/ Winter 2027 through Summer 2028
- Land Use Permit – Spring 2028
- Construction Begins – Summer 2028