Accotink Pump Station Rehabilitation Project - Construction Summary
Public Works and Environmental Services Alert:
CONTACT INFORMATION:
Our administrative offices are open to the public. Appointments are preferred. Please call or email 8 a.m. - 4:30 p.m., Monday – Friday
Accotink Pump Station Rehabilitation Project - Construction Summary
2024-05-16T11:00:00
2024-05-16T11:00:00
Scope: Rehabilitate the mechanical components of the Accotink Pump Station and replace the force main. This project follows the generator and switchgear replacement projects, completed in 2007 and 2016, respectively. Most of the mechanical components were installed in 1977 except for the pumps, which were replaced in 1998. These components have reached the end of their useful lives.