Timeline
Construction: Summer, 2024 – Fall, 2028
What to expect
The work associated with the pump station will take place in the vicinity of the existing pump station at 9201 Richmond Highway. The new force main will be constructed in an area adjacent to the existing pipe in a cross-country area located in an easement on Ft. Belvoir property. A portion of the breakdown lane will be closed on Richmond Highway in the vicinity of Fairfax County Parkway to assure driver and construction safety and to minimize traffic impacts on deliveries to the construction site.
Project Cost and Funding Source
The construction for this project was awarded in the amount of $71.7M. The project is being funded through Sewer Use fees.
Contact
For more information, please contact the Project Manager, Thomas Grala at thomas.grala@fairfaxcounty.gov, or call 571-230-8269, TTY 711.