Accotink Pump Station Rehabilitation

Project WW-000001-013

Project Update: August 1, 2024

The construction contract has been recently awarded and coordination of construction activities has begun.


Project Background

The Accotink Pump Station Rehabilitation project is being completed as part of a program that evaluates current station condition and capacity. Improvements to this station have been identified to provide reliable service for the service area and upgrade equipment that has reached the end of its useful life.

Project Description

This project will rehabilitate the existing pump station by replacing equipment that has reached its useful life, expand pump station capacity to meet future growth needs, and replace the existing force main servicing the station. The contract has been awarded to Northeast Remsco Construction, Inc. and is included in the FY 2025-FY 2029 Adopted Capital Improvement Program (With Future Fiscal Years to FY 2034). The construction contract for this project will include a Project Labor Agreement (PLA).

Project Location

Map - Accotink Pump Station

Project Phase

Construction

Timeline

Construction: Summer, 2024 – Fall, 2028

What to expect

The work associated with the pump station will take place in the vicinity of the existing pump station at 9201 Richmond Highway. The new force main will be constructed in an area adjacent to the existing pipe in a cross-country area located in an easement on Ft. Belvoir property. A portion of the breakdown lane will be closed on Richmond Highway in the vicinity of Fairfax County Parkway to assure driver and construction safety and to minimize traffic impacts on deliveries to the construction site.

Project Cost and Funding Source

The construction for this project was awarded in the amount of $71.7M. The project is being funded through Sewer Use fees.

Contact

For more information, please contact the Project Manager, Thomas Grala at thomas.grala@fairfaxcounty.gov, or call 571-230-8269, TTY 711.