Timeline
June 29, 2026 – October 27, 2026

Timeline – Phase 1 (Parking lot B)
| Area A | 06/29/2026 – 08/07/2026 |
| Area B | 06/29/2026 – 08/07/2026 |
| Area C | 08/10/2026 – 09/30/2026 |
| Area D | 06/29/2026 – 10/27/2026 |
Timeline – Phase 2 (Parking lot A)
| Area E | 08/17/2026 – 09/25/2026 |
| Area F | 08/17/2026 – 09/25/2026 |
| Area G | 08/17/2026 – 09/25/2026 |
What to Expect
There will be partial closures in Parking lots A and B during construction. Clear signage and direction will be provided for pedestrians and vehicles. During each phase, parking spaces will be limited. We encourage employees to avoid parking in these areas and utilize other parking lots C and D.


Parking Relocation Map During Phase 2
Project Cost
$1,568,873
Contact
For more information, please email Lut Tang Jerome Lam, Project Manager/Construction Manager or call 571-407-6704.