Timeline
- 35% Design: Complete
- 70% Design: Complete
- Land (Easement) Acquisition Start: Summer 2025
- Land (Easement) Acquisition End: Fall 2026
- 95% Design Completion: Complete
- Bid Ready Documents: Fall 2026
- Construction Bid Advertisement: Late Fall 2026
- Construction Contract Award: Spring 2027
- Construction Notice-to-Proceed: Spring 2027
- Construction Substantial Completion: Fall 2028
What to Expect
While the project is being designed, people might see survey teams and engineers gathering information in the area. There were two community meetings planned to present the design. The first meeting was held March 20, 2025. The second meeting will be held April 30, 2026. Property owners who need to grant easements were contacted by a Fairfax County agent in mid-2025. Construction is expected to start in Spring 2027 and be completed in Fall 2028.
Project Cost and Funding Source
Construction for this project is expected to cost $9.9 million. Funding for this project comes from sewer use and connection fees paid by people using and connecting to the sewer system.
Presentation to the Community
The second of the two planned community outreach meetings was held Thursday, April 30, 2026, at 7:00 PM on Microsoft Teams.
The first of two planned community outreach meetings was held Thursday, March 20, 2025, at 7 p.m. on Microsoft Teams.
The second community outreach meeting is scheduled for Thursday, April 30, 2026, at 7:00 PM on Microsoft Teams. To receive a link to this online meeting, please email Natasha Schmidt and include your name, address, and phone number in the email.
Contact
For questions about the project, please contact project manager Natasha Schmidt, call 703-324-5080, TTY 711, or call 571-407-4529.