Public Works and Environmental Services

CONTACT INFORMATION: Our administrative offices are open to the public. Appointments are preferred. Please call or email 8 a.m. - 4:30 p.m., Monday – Friday
703-324-5800 TTY 711
12000 Government Center Parkway
Suite 449 Fairfax, VA 22035
Carey Needham
Director, Capital Facilities

Lake Barcroft Odor Control Project

Project Number: WW-000001-022

Project Update: January 29, 2024

Architect/Engineer (AE) is working on easements and plats with the County Attorney and Land Acquisition Division. Conducted with Dominion Energy and COX regarding power and SCADA for the Odor Control Unit. AE amendment to the contract was approved by the County.


Project Background

The Fairfax County Department of Public Works and Environmental Services (DPWES) has received multiple odor complaints related to the wastewater collection system in the vicinity of Columbia Pike and Lake Barcroft. In February 2020, our consultant completed an evaluation report and recommended implementation of a vapor phase odor control system within the Holmes Run Stream Valley Park. This was followed by a more detailed evaluation and a pilot study which concluded in the Fall of 2021.

Project Description

The goal of the project is to mitigate sewer related odors along an approximate one-mile-long area within the Holmes Run Stream Valley Park south of Columbia Pike. The project consists of installing a vapor-phase odor control unit (7,000 cfm carbon adsorption unit) near Holmes Run, inlet duct work and plenum, discharge duct work and dispersion stack, 13 manhole air inlet assemblies including isolation valves, and up to 1,500 feet of underground 12 to 16-inch diameter jumper ventilation lines between manholes to maximize odor removal farther upstream and downstream from the odor control facility.

Project Location

The project is in the Lilian Carey and Holmes Run Stream Valley Parks south of Columbia Pike. The carbon adsorber and dispersion stack will be located just before the first stream crossing near Manholes 22 & 27 as shown on the figures below. An example carbon adsorber and air inlet (gooseneck) assembly is shown in the photos below.

Sewer lines and Manhole Locations
Sewer lines and Manhole Locations
Carbon Adsorber Unit Diagram and Photo; Manhole Air Inlet Assembly
Carbon Adsorber Unit Diagram and Photo; Manhole Air Inlet Assembly

Project Phase

Final Design

Project Benefits

  • Minimizing sewer odors within Lilian Carey Park and the Holmes Run Stream Valley Park.
  • Reduction of H2S and other odorous compounds inside the wastewater collection system for improved safety and to help prolong the life of the sewer system.

Timeline

The project is expected to be bid during the 4th Quarter of 2023. Construction is expected to begin in the 1st Quarter of 2024 and be substantially complete in the 1st Quarter of 2025. The schedule is subject to change.

What To Expect

This new ventilation system will significantly reduce odors within and around the Lilian Carey and Holmes Run Stream Valley Parks.

Project Cost and Funding Source

The Current total project estimate for this project is $5,619,274, which will be funded through the County’s Capital Improvement Program (CIP).

CONTACT

For information, please email mujahid.ali@fairfaxcounty.gov, Mujahid Ali, P.E., AVS; Sr. Project Manager, Wastewater Design and Construction Division, Department of Public Works, and Environmental Services.

Fairfax Virtual Assistant