Timeline
June 29, 2026 – October 27, 2026

Timeline – Phase 1 (Parking lot B)
| Area A | 06/29/2026 – 09/30/2026 |
| Area B | 06/29/2026 – 09/30/2026 |
| Area C | 08/03/2026 – 08/21/2026 |
| Area D | 06/29/2026 – 10/27/2026 |
Timeline – Phase 2 (Parking lot A)
| Area E | 08/03/2026 – 10/09/2026 |
| Area F | 08/03/2026 – 10/09/2026 |
| Area G | 08/03/2026 – 10/09/2026 |
What to Expect
- During each phase, parking spaces will be limited. We encourage employees to avoid parking in these areas and utilize other parking lots C and D.
- Clear signage and direction will be provided for pedestrians and vehicles.


Parking Relocation Map During Phase 2
Project Cost
$1,568,873